vendredi 27 mars 2015

MARTA P25 Upgrade???

Anyone know when MARTA is planned to switch over to P25?



It's mentioned here:

MARTA - Metropolitan Atlanta Rapid Transit Authority





A 7-Year 4-Phased approach 2011-2017



Planning Phase of the project, which has been completed, involved assessment of the state of the radio communications networks within all Marta operational areas including Police and Rail.



Phase 1 of the project is underway and consists of requirements, system design, and procurement for the P25 IP Core, SmartX Gateway, MGEG and a software upgrade to the Gold Elite dispatch consoles. The goal is that the resulting system will be backward compatible with the previous SmartZone 4.1 system and 800 MHz analog subscriber units.



Phase 2 involves procurement and installation of the repeater sites, replacement of BDA assets in tunnels and stations, and assessment of competitive solutions for portable units.



Phase 3 involves procurement and commissioning of mobile and portable units and build out of additional repeater sites if necessary



Upcoming Milestones:

Cutover to operation of P25 Interoperable Core to full production operations - January 17, 2014

Completion of P25 Interoperable Core activities - March 31, 2014

Initiation of activities to replace bi-directional amplifier for tunnels and stations - January 1, 2014

Initiation of activities to replace site base station element - June 1, 2014





MARTA P25 Upgrade???

Aucun commentaire:

Enregistrer un commentaire